FREEMAN WELCOMES EXECUTIVE ORDER EMPOWERING DOMESTIC MINERAL PRODUCTION

VANCOUVER, BRITISH COLUMBIA – March 26, 2025 – Freeman Gold Corp. (TSXV: FMAN, OTCQB: FMANF, FSE: 3WU) (“Freeman” or the “Company”) welcomes President Donald Trump’s  Executive Order to fast-track and revitalize American mineral production (the “Order”). Among its provisions, the Executive Order empowers use of the Defense Production Act to elevate domestic production capabilities and provides for […]

FREEMAN APPOINTS AUSENCO TO LEAD LEMHI GOLD PROJECT FEASIBILITY STUDY

VANCOUVER, BRITISH COLUMBIA – February 10, 2025 – Freeman Gold Corp. (TSXV: FMAN, OTCQB: FMANF, FSE: 3WU) (“Freeman” or the “Company”) is pleased to announce the appointment of Ausenco Engineering Canada ULC (“Ausenco”) to lead the Lemhi Gold Project Feasibility Study (the “FS”), following a competitive bidding process. The Lemhi Gold Project (the “Project” or […]

FREEMAN APPOINTS DAVID KEOUGH TO ITS BOARD OF DIRECTORS

VANCOUVER, BRITISH COLUMBIA – December 2, 2024 – Freeman Gold Corp. (TSX-V: FMAN, OTCQB: FMANF, FSE: 3WU) (“Freeman Gold”, “Freeman” or the “Company”) is pleased to announce it has appointed David Keough to its board of directors, effective December 2, 2024. Mr. Keough is an experienced mining executive with over 35 years of practice in […]

FREEMAN FILES PRELIMINARY ECONOMIC ASSESSMENT TECHNICAL REPORT FOR LEMHI GOLD PROJECT

TSX Venture Exchange: FMAN VANCOUVER, BRITISH COLUMBIA – November 30, 2023 – Freeman Gold Corp. (TSXV: FMAN, OTCQX: FMANF, FSE: 3WU) (“Freeman” or the “Company”) is pleased to announce that it has filed a National Instrument (“NI”) 43-101 Technical Report entitled “Lemhi Gold Project, NI 43-101 Technical Report and Preliminary Economic Assessment, Idaho, United States” […]

FREEMAN IMPROVES AVERAGE GOLD RECOVERIES TO 96.9% AND LEACH CIRCUIT TIME BY 50% FOR THE LEMHI GOLD DEPOSIT, IDAHO

Freeman has recently received metallurgical results from tests conducted on two composite samples by Base Metallurgical Laboratories Limited, Kamloops, in conjunction with Ausenco Engineering Canada Ltd. The final metallurgical flowsheet resulted in significant cost savings and operational efficiencies. These include: 5-10% reduction in energy costs associated with milling; 50% reduction in leach circuit time from […]