FREEMAN ANNOUNCES POST-TAX NPV5% of US$648 MILLION USING US$2,900 GOLD PRICE FOR THE LEMHI GOLD PROJECT LOCATED IN IDAHO, USA

VANCOUVER, BRITISH COLUMBIA – April 9, 2025 – Freeman Gold Corp. (TSXV: FMAN, OTCQB: FMANF, FSE: 3WU) (“Freeman” or the “Company”) is pleased to announce the results of its updated price sensitivity analysis using current market prices completed by Ausenco Engineering Canada ULC (“Ausenco”) and Moose Mountain Technical Services (“MMTS”). Updating the pricing used in the October 16, 2023 initial Preliminary Economic Assessment (“PEA”) at a base case of US$2,200/oz gold price, based on current long-term consensus forecasts, results in a post-tax Net Present Value (“NPV”)5%  of US$329 million, a post-tax internal rate of return (“IRR”) of 28.2% and a payback of 2.9 years. This analysis quantifies the strong leverage to gold and is a marked improvement over the original base case of US$1,750/oz gold price resulting in a post-tax NPV5% of US$212 million, a post-tax IRR of 22.8% and a payback of 3.6 years. The updated price analysis demonstrates that the Lemhi Gold Project’s economics remain strong with significant leverage to the current spot price of US$2,900/oz which results in a post-tax NPV5%  of US$648 million, post-tax IRR of 45.9% and a payback of 2.1 years. Figure 1 summarizes the various post-tax NPV5% for gold prices ranging from US$1,750/oz to US$3,400/oz.

Figure 1: Post-Tax NPV5% at Various Gold Prices

“Significant changes in gold prices over the last 18 months motivated Freeman’s reassessment of its initial PEA model over a more fulsome range of scenarios. Using the current spot gold price, the Lemhi Gold Project will have an approximate US$1,871/oz cash margin using the updated all in sustaining cost (“AISC”) of US$1,105/oz with significant additional upside at higher prices. The Lemhi Gold Project remains a low capital expenditure (“CAPEX”), low-cost project that is profitable across a range of prices and development options,” commented Bassam Moubarak, the Company’s Chief Executive Officer.  “Furthermore, this updated economic analysis using a US$2,200/oz gold base case further solidifies the after-tax NPV (5%) at US$329 million, a post-tax IRR of 28.2% and reduces the payback to 2.9 years.”

Updated Economic Analysis

The updated Economic Analysis is based on the production and mining profile used in the 2023 PEA. Table 1 provides a summary of the production profile along with the updated project price economics.

Table 1: Updated Economic Analysis Summary

GeneralUnitLife-of-Mine (“LOM”) Total/Avg.
Gold PriceUS$/oz2,200
Mine Lifeyears11.2
Total Waste Tonnes Minedkt121,903
Total Mill Feed Tonneskt31,128
ProductionUnitLOM Total/Avg.
Strip Ratiowaste: mineralized rock3.9
Mill Head Gradeg/t0.88
Mill Recovery Rate%96.7
Total Payable Mill Ounces Recoveredkoz851.9
Total Average Annual Payable Productionkoz75.9
Operating Costs UnitLOM Total/Avg.
Mining Cost (incl. rehandle)US$/t mined2.96
Mining Cost (incl. rehandle)US$/t milled13.49
Processing CostUS$/t milled10.91
General & Administrative CostUS$/t milled1.14
Total Operating CostsUS$/t milled25.54
Treatment & Refining CostUS$/oz4.3
Net Smelter Royalty%1
Cash Costs1US$/oz Au925
All-In Sustaining Costs2US$/oz Au1,105
Capital CostsUnitLOM Total/Avg.
Initial CapitalUS$M215
Expansion Capital3US$M6.5
Sustaining CapitalUS$M105
Closure CostsUS$M33
Salvage ValueUS$M14
Financials – Pre-TaxUnitLOM Total/Avg.
Net Present Value (5%)US$M453
Internal Rate of Return%33.2
Paybackyears2.7
Financials – Post-TaxUnitLOM Total/Avg.
Net Present Value (5%)US$M329
Internal Rate of Return%28.2
Paybackyears2.9

Notes:

  1. Cash costs consist of mining costs, processing costs, mine-level G&A and treatment and refining charges.
  2. All-in sustaining costs include cash costs plus royalties, sustaining capital and closure costs.
  3. Expansion of mill from 2.5 million tonnes per annum (“Mtpa”) to 3 Mtpa in year 5 of operation


Capital & Operating Costs

The updated capital cost estimate conforms to Class 5 guidelines for a PEA-level estimate accuracy according to the Association for the Advancement of Cost Engineering International. The capital cost estimate was developed in Q1 2025 United States dollars based on Ausenco’s in-house database of projects and studies, as well as experience from similar operations and escalation of costs from 2023 PEA.

The updated estimate includes open pit mining, processing, on-site infrastructure, tailings and waste rock facilities, off-site infrastructure, project indirect costs, project delivery, owner’s costs, and contingency. The updated capital cost summary is presented in Table 2. The updated total initial capital cost for the Lemhi Project is US$214.9 million; and life-of-mine sustaining costs are US$104.8 million. The updated cost of expansion in the fifth year of production is estimated at US$6.5 million. Updated Closure costs are estimated at US$32.6 million, with salvage credits of US$13.9 million.

Table 2: Updated Summary of Capital Cost

Work Breakdown StructureWBS DescriptionInitial Capital Cost (US$M)Sustaining Capital Cost LOM (US$M)Expansion Cost (US$M)Total Capital Cost LOM (US$M) 
1000Mine52.063.02.2117.2
3000Process Plant73.51.72.777.9
4000Tailings10.739.950.6
5000On-Site Infrastructure20.20.220.4
6000Off-Site Infrastructure2.52.5
Total Directs158.9104.84.9268.6
7100Field Indirects6.90.27.1
7200Project Delivery12.80.313.1
7500Spares + First Fills3.20.23.4
8000Owner’s Cost4.24.2
Total Indirects27.10.727.8
9000Contingency28.90.929.8
Project Total214.9104.86.5326.2

Sensitivity Analysis

A sensitivity analysis was conducted on the base case post-tax NPV5% and IRR of the project using the following variables: gold price, operating costs, and initial capital costs. Table 3 summarizes the post-tax sensitivity analysis results.

Table 3: Post-Tax Sensitivity Analysis

Post-Tax NPV5%  Sensitivity To OpexPost-Tax IRR Sensitivity To Opex
Gold Price (US$/oz)Gold Price (US$/oz)
#VALUE!$1,600$1,750$2,200$2,600$3,400Opex#VALUE!$1,600$1,750$2,200$2,600$3,400
(20.0%)141210415597962(20.0%)16.0%20.7%33.3%43.3%61.7%
(10.0%)97166372554919(10.0%)12.8%17.8%30.8%40.9%59.6%
531233295118769.4%14.7%28.2%38.6%57.4%
10.0%97928646883310.0%5.7%11.4%25.5%36.2%55.3%
20.0%-363524242579020.0%1.9%7.9%22.7%33.7%53.1%
Post-Tax NPV Sensitivity To Initial CapexPost-Tax IRR Sensitivity To Initial Capex
Gold Price (US$/oz)Gold Price (US$/oz)
#VALUE! $1,600  $1,750  $2,200  $2,600  $3,400 Initial Capex#VALUE! $1,600  $1,750  $2,200  $2,600  $3,400 
(20.0%)97166373555919(20.0%)14.2%20.3%36.1%48.3%70.9%
(10.0%)75145351533898(10.0%)11.6%17.3%31.8%43.0%63.5%
531233295118769.4%14.7%28.2%38.6%57.4%
10.0%3110130749085410.0%7.4%12.5%25.2%34.9%52.4%
20.0%107928546883220.0%5.7%10.5%22.6%31.7%48.2%

Qualified Persons and Technical Disclosure

A team of Independent Qualified Persons (as such term is defined under National Instrument 43-101 (“NI 43-101)) at Ausenco and MMTS led the price sensitivity analysis and has reviewed and verified the technical disclosure in this press release. The team of Independent Qualified Persons, includes:

  • Kevin Murray, P.Eng., an independent Qualified Person at Ausenco, reviewed and verified the process and infrastructure capital and operating cost estimation, and project financials; and
  • Marc Schulte, P.Eng.,  an independent Qualified Person at MMTS, reviewed and verified the mine planning and cost estimation.

The scientific and technical information in this news release has been reviewed and verified by Dean Besserer, P.Geo., Vice-President of Exploration of the Company and Qualified Person as defined in NI 43-101.

The updated sensitivity analysis in respect of the PEA is preliminary in nature, it includes inferred mineral resources considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves, and there is no certainty that the PEA will be realized. For a discussion on the basis and the qualifications and assumptions of the sensitivity analysis, please see the PEA entitled “Lemhi Gold Project, NI 43-101 Technical Report and Preliminary Economic Assessment” dated with an effective date of October 13, 2023, and available on SEDAR+ (www.sedarplus.ca) and the Company’s website (www.freemangoldcorp.com).

About the Company and Project

Freeman Gold Corp. is a mineral exploration company focused on the development of its 100% owned Lemhi Gold property. The Lemhi Gold Project comprises 30 square kilometres of highly prospective land, hosting a near-surface oxide gold resource. The pit constrained NI 43-101 compliant mineral resource estimate is comprised of 988,100 ounces gold (“oz Au”) at 1.0 gram per tonne (“g/t”) in 30.02 million tonnes (Measured & Indicated) and 256,000 oz Au at 1.04 g/t Au in 7.63 million tonnes (Inferred). The Company is focused on growing and advancing the Lemhi Gold Project towards a production decision. To date, 525 drill holes and 92,696 m of drilling has historically been completed.

The recently updated price sensitivity analysis shows a PEA with an after-tax net present value (5%) of US$329 million and an internal rate of return of 28.2% using a base case gold price of US$2,200/oz; Average annual gold production of 75,900 oz Au for a total life-of-mine of 11.2 years payable output of 851,900 oz Au; life-of-mine cash costs of US$925/oz Au; and, all-in sustaining costs of US$1,105/oz Au using an initial capital expenditure of US$215 million.

On Behalf of the Company

Bassam Moubarak

Chief Executive Officer

  • For further information, please visit the Company’s website at www.freemangoldcorp.com or contact Mr. Bassam Moubarak at by email at bm@bmstrategiccapital.com .
  •  
  • Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Forward-Looking Statements: This press release contains “forward‐looking information or statements” within the meaning of Canadian securities laws, which may include, but are not limited to, all statements related to the PEA, statements relating to exploration, results therefrom, and the Company’s future business plans, and statements regarding the price sensitivity analysis and impact thereof on the evaluation of the Project’s economic potential. All statements in this release, other than statements of historical facts that address events or developments that the Company expects to occur, are forward-looking statements. Forward-looking statements are statements that are not historical facts and are generally, but not always, identified by the words “expects,” “plans”, “anticipates”, “believes”, “intends”, “estimates”, “projects”, “potential” and similar expressions, or that events or conditions “will”, “would”, “may”, “could” or “should” occur. Although the Company believes the expectations expressed in such forward-looking statements are based on reasonable assumptions, such statements are not guarantees of future performance and actual results may differ from those in the forward-looking statements. Such forward-looking information reflects the Company’s views with respect to future events and is subject to risks, uncertainties, and assumptions. The reader is urged to refer to the Company’s reports, publicly available through the Canadian Securities Administrators’ web-based disclosure system, SEDAR+, at www.sedarplus.ca for a more complete discussion of such risk factors and their potential effects. The Company does not undertake to update forward‐looking statements or forward‐looking information, except as required by law.

Receive Updates

Get exclusive updates delivered right to your inbox but subscribing to our mailing list. 

Share

Facebook
Twitter
LinkedIn

Related News